Timeline: setting out the estimated timescales for how we will apply this plan (accessible version)
Updated 27 July 2021
Estimated timescales to apply water abstraction plan.
2018
Environment
- changes to Time Limited Licences � continues
- revocation of unused licences � continues
- changes to highest priority licences � continues
Catchment focus
- trial approach to improving access to water commences in four catchments
Abstraction licensing service
January 2018:
- licence application process for previously exempt abstractions opens
- start testing digital abstraction licences
2019
Environment
- water companies investigate risks from licences at catchment scale � continues
Catchment focus
- Environment Agency trial approaches at catchment scale to improve access to water in four catchments and to make environmental improvements in six
Abstraction licensing service
- by end 2019 � majority of licences available digitally and approach to submitting records online is improved
2020
Environment
- Environment Agency complete restoring sustainable abstraction programme
Catchment focus
-
Environment Agency publish four updated abstraction licensing strategies from trial catchments
-
Environment Agency continue to develop environmental solutions in six initial catchments
Abstraction licensing service
-
January � licence determinations for previously exempt abstractions begin
-
30 June � applications close for previously exempt abstractions
-
tailored information on flows and levels available online for some licences
2021
Catchment focus
-
Environment Agency publish a further six updated licensing strategies � based on catchment engagement
-
Environment Agency shifts focus to different catchments and improves approach based on experience
-
Environment Agency reports to government on progress made on improving access to water and addressing environmental issues
Abstraction licensing service
- Spring 2021 � Defra consult on move to Environmental Permitting Regulations
2022
Catchment focus
-
Environment Agency continue to publish updated abstraction licensing strategies to support 3rd cycle of river basin planning - this will start with the highest priority catchments
-
All strategies to be updated by 2027.
Abstraction licensing service
- by December � all previously exempt abstractions will be permitted.
2023
Abstraction licensing service
-
by 31 December � abstraction and impounding moves into the Environmental Permitting Regulations and all existing abstraction and impounding licences become environmental permits
-
applications for a permit are available online